The Hydes Estate Solar PV

The Hydes Estate Solar PV, Push Energy, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 9 MW, grid supply point Pelham.

Customer
Push Energy
Status
Connected
Capacity
9 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Voltage
33 kV
Date connected
18 Dec 2014
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Little Barfield, Braintree
Postcode
CM7 4TY
Export MPAN
1050000759722

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.