Thanet Windfarm

Thanet Windfarm, National Grid Electricity Transmission PLC, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 315 MW, grid supply point Richborough/Sellindge 132kV.

Customer
National Grid Electricity Transmission PLC
Status
Connected
Capacity
315 MW
Technology
Offshore wind (Offshore wind turbines)
Flexible connection
No
Grid supply point
Richborough/Sellindge 132kV
Voltage
132 kV
Date connected
29 Sept 2010
In a connection queue
No
Row last updated by the DNO
15 Jan 2021
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Richborough Power Station, Richborough
Postcode
CT13 9QN
Export MPAN
1999000000443

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source