Thanet Energy
Thanet Energy, Thanet Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Richborough/Sellindge 132kV.
- Customer
- Thanet Energy Limited
- Status
- Connected
- Capacity
- 30 MW
- Technology
- Gas (Steam-gas turbine (CCGT))
- Flexible connection
- No
- Grid supply point
- Richborough/Sellindge 132kV
- Voltage
- 33 kV
- Date connected
- 23 Apr 2009
- In a connection queue
- No
- Row last updated by the DNO
- 14 Oct 2022
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Seamark Road, Birchington
- Postcode
- CT7 0JL
- Export MPAN
- 1998000000024
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.