Temple Farm
Temple Farm, Crofton Design, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.7 MW, grid supply point Rayleigh.
- Customer
- Crofton Design
- Status
- Connected
- Capacity
- 1.7 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- Rayleigh
- Bulk supply point
- Chelmsford East Grid 33kV
- Point of connection
- West Hanningfield Pri 11kV
- Voltage
- 11 kV
- Date connected
- 23 Apr 2019
- In a connection queue
- No
- Row last updated by the DNO
- 14 Feb 2024
- Licence area
- EPN
- Address
- Ship Road, Chelmsford
- Postcode
- CM2 8XB
- Export MPAN
- 1050001368485
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.