Spriggs Farm

Spriggs Farm, DNO Consulting Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Pelham.

Customer
DNO Consulting Limited
Status
Connected
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Voltage
33 kV
Date connected
24 Sept 2013
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Little Sampford, Saffron Walden
Postcode
CB10 2SA
Export MPAN
1050000540028

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.