Southend STW

Southend STW, Anglian Water Services Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3.2 MW, grid supply point Rayleigh.

Customer
Anglian Water Services Limited
Status
Connected
Capacity
3.2 MW
Technology
Fossil - Oil (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Rayleigh
Bulk supply point
Fleethall Grid 33kV
Point of connection
Fleethall Local Primary 11kV
Voltage
11 kV
Date connected
1 Oct 1999
In a connection queue
No
Row last updated by the DNO
14 Dec 2021
Licence area
EPN
Address
Southend
Postcode
SS2 5QF
Export MPAN
1023477429636

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.