Grid GuardianOpen the evidence in the app

Sevington Generation

Sevington Generation, UK Power Reserve Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10 MW, grid supply point Richborough/Sellindge 132kV.

Customer
UK Power Reserve Limited
Status
Connected
Capacity
10 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Richborough/Sellindge 132kV
Bulk supply point
Ashford Grid 33kV
Point of connection
Sevington 11kV
Voltage
11 kV
Date connected
6 Jun 2002
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
The Long Barrow, Ashford
Postcode
TN24 0GP
Export MPAN
1900091173770

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source