Grid GuardianOpen the evidence in the app

Ryston Estate

Ryston Estate, Enray Power Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12.5 MW, grid supply point Walpole.

Customer
Enray Power Limited
Status
Accepted to connect
Capacity
12.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
Kings Lynn South Grid 132/33kV
Point of connection
Downham market primary 33/11kV
Voltage
33 kV
Date accepted
3 May 2026
In a connection queue
Yes
Row last updated by the DNO
13 Mar 2026
Licence area
EPN
Address
Ryston, Downham Market
Postcode
PE38 OAA

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source