Grid GuardianOpen the evidence in the app

Royston Solar Farm A505 Royston Bypass

Royston Solar Farm A505 Royston Bypass, Solar Planning Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 7.5 MW, grid supply point Wymondley.

Customer
Solar Planning Limited
Status
Connected
Capacity
7.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Melbourn Grid 33kV
Voltage
33 kV
Date connected
16 Dec 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Royston
Postcode
SG8 5UT
Export MPAN
1050000996114

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.