Rayleigh Site

Rayleigh Site, HD192RAY Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 99.8 MW, grid supply point Rayleigh.

Customer
HD192RAY Limited
Status
Accepted to connect
Capacity
99.8 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Rayleigh
Voltage
132 kV
Date accepted
16 Sept 2020
Target energisation
6 Jan 2025
In a connection queue
Yes
Row last updated by the DNO
13 Oct 2023
Licence area
EPN
Address
Wickford
Postcode
SS11 8TZ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.