Grid GuardianOpen the evidence in the app

Peterborough Power Station

Peterborough Power Station, Centrica PB Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 337.5 MW, grid supply point Walpole.

Customer
Centrica PB Limited
Status
Connected
Capacity
337.5 MW
Technology
Gas (Steam-gas turbine (CCGT))
Flexible connection
No
Grid supply point
Walpole
Voltage
132 kV
Date connected
13 Dec 1990, 20 Aug 2018
In a connection queue
No
Row last updated by the DNO
14 Mar 2024
Licence area
EPN
Address
Storey Bar Road, Peterborough
Postcode
PE1 5NT
Export MPAN
1097000000100, 1050001368332

Register rows

RowStatusMWTarget
1Connected337.5
2Connected48.5

Rows at one site are not summed.

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source