Northwest Of Childs Farm

Northwest Of Childs Farm, RES Development Company 18 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Wymondley.

Customer
RES Development Company 18 Limited
Status
Accepted to connect
Capacity
49.9 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Wymondley
Voltage
132 kV
Date accepted
15 Sept 2022
Target energisation
31 Oct 2032
In a connection queue
Yes
Row last updated by the DNO
14 Jul 2024
Licence area
EPN
Address
Cottered
Postcode
SG9 9PU

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.