Grid GuardianOpen the evidence in the app

Manor Farm

Manor Farm, IG Renewables Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.9 MW, grid supply point Wymondley.

Customer
IG Renewables Limited
Status
Accepted to connect
Capacity
4.9 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Wymondley
Bulk supply point
Melbourn Grid 132/33kV
Point of connection
Shepreth 11kV
Voltage
11 kV
Date accepted
17 Apr 2026
In a connection queue
Yes
Row last updated by the DNO
15 May 2026
Licence area
EPN
Address
Frog End, Royston
Postcode
SG8 6RE

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source