Lower Dunton Road

Lower Dunton Road, Cedartech Energy Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 98 MW, grid supply point Warley.

Customer
Cedartech Energy Limited
Status
Accepted to connect
Capacity
98 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Warley
Voltage
132 kV
Date accepted
24 Sept 2024
In a connection queue
Yes
Row last updated by the DNO
13 Dec 2024
Licence area
EPN
Address
Upminster
Postcode
RM14 3TD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.