Lords Way, PeakGen Power Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Rayleigh.

Customer
PeakGen Power Limited
Status
Connected
Capacity
20 MW
Maximum import capacity
0.5 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Rayleigh
Bulk supply point
Nevendon Grid 33kV
Voltage
132 kV
Date connected
19 Feb 2021
In a connection queue
No
Row last updated by the DNO
14 Dec 2021
Licence area
EPN
Address
Basildon
Postcode
SS13 1DB
Export MPAN
1050001905679
Import MPAN
1050001905660

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.