Long Barrow

Long Barrow, UK Power Reserve Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.6 MW, grid supply point Richborough/Sellindge 132kV.

Customer
UK Power Reserve Limited
Status
Connected
Capacity
4.6 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Richborough/Sellindge 132kV
Bulk supply point
Ashford Grid 33kV
Point of connection
Sevington 11kV
Voltage
11 kV
Date connected
1 Dec 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Orbital Park, Ashford
Postcode
TN24 0GP
Export MPAN
1900091173770

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source