Grid GuardianOpen the evidence in the app

Little Cheyne Court Windfarm

Little Cheyne Court Windfarm, Little Cheyne Court Wind Farm, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 64 MW, grid supply point Ninfield.

Customer
Little Cheyne Court Wind Farm
Status
Connected
Capacity
64 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Ninfield
Voltage
132 kV
Date connected
7 Jan 2008
In a connection queue
No
Row last updated by the DNO
15 Jan 2021
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Rye, Guildford
Postcode
TN31 7AE
Export MPAN
1900090194644

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source