Land On The West Side Of Selling Road

Land On The West Side Of Selling Road, Ilos New Energy UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 18 MW, grid supply point Kemsley.

Customer
Ilos New Energy UK Limited
Status
Accepted to connect
Capacity
18 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Kemsley
Bulk supply point
Sittingbourne
Voltage
33 kV
Date accepted
20 Oct 2025
In a connection queue
Yes
Row last updated by the DNO
12 Dec 2025
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Westwood Court, Selling
Postcode
ME13 9QE

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.