Land off Old Ferry Road

Land off Old Ferry Road, Enviromena Project Management UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.9 MW, grid supply point Kemsley.

Customer
Enviromena Project Management UK Limited
Status
Accepted to connect
Capacity
4.9 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Kemsley
Bulk supply point
Grovehurst Grid
Point of connection
Grovehurst Local
Voltage
11 kV
Date accepted
26 Jun 2026
In a connection queue
Yes
Row last updated by the DNO
14 Jul 2026
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Iwade, Sittingbourne
Postcode
ME9 8SW

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.