Grid GuardianOpen the evidence in the app

Land At St Thomas Lane

Land At St Thomas Lane, BSR Applications, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 99.9 MW, grid supply point Norwich.

Customer
BSR Applications
Status
Accepted to connect
Capacity
99.9 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Norwich
Voltage
132 kV
Date accepted
23 Apr 2026
In a connection queue
Yes
Row last updated by the DNO
15 May 2026
Licence area
EPN
Address
Kettingham, Wymondham
Postcode
NR18 9RP

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source