Land At Holly Farm
Land At Holly Farm, BSR Applications, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 13 MW, grid supply point Norwich.
- Customer
- BSR Applications
- Status
- Accepted to connect
- Capacity
- 13 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Norwich
- Bulk supply point
- Trowse Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 26 Mar 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 16 Apr 2026
- Licence area
- EPN
- Address
- Catfield, Great Yarmouth
- Postcode
- NR29 5DF
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.