Land Adjoining The Wallburys
Land Adjoining The Wallburys, IG Renewables Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3.6 MW, grid supply point Pelham.
- Customer
- IG Renewables Limited
- Status
- Accepted to connect
- Capacity
- 3.6 MW
- Technology
- Solar, Storage (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Pelham
- Bulk supply point
- Bishops Stortford Grid 33kV
- Point of connection
- Thorley Primary 11kV
- Voltage
- 11 kV
- Date accepted
- 16 Sept 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Oct 2026
- Licence area
- EPN
- Address
- Land Lying To The West Of Great Hallingbury, Bishops Stortford
- Postcode
- CM22 7SQ
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.