Kentish Farm 2

Kentish Farm 2, Kentish Solar Farm 3 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3.2 MW, grid supply point Braintree.

Customer
Kentish Solar Farm 3 Limited
Status
Accepted to connect
Capacity
3.2 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Braintree
Bulk supply point
Braintree Local 33kV
Voltage
33 kV
Date accepted
29 Sept 2017
Target energisation
6 Jan 2025
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Braintree
Postcode
CM77 8BX

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.