Ironsbottom Solar Farm
Ironsbottom Solar Farm, Luminous Energy Group Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Bolney.
- Customer
- Luminous Energy Group Limited
- Status
- Accepted to connect
- Capacity
- 30 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Bolney
- Bulk supply point
- Leigh Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 23 Nov 2021
- Target energisation
- 31 Dec 2030
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Jun 2024
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Ironsbottom, Reigate
- Postcode
- RH2 8PT
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.