Grid GuardianOpen the evidence in the app

Ironsbottom Solar Farm

Ironsbottom Solar Farm, Luminous Energy Group Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Bolney.

Customer
Luminous Energy Group Limited
Status
Accepted to connect
Capacity
30 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bolney
Bulk supply point
Leigh Grid 33kV
Voltage
33 kV
Date accepted
23 Nov 2021
Target energisation
31 Dec 2030
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Ironsbottom, Reigate
Postcode
RH2 8PT

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.