Horseley FEN AD Generation Aka FDG A-15

Horseley FEN AD Generation Aka FDG A-15, Forenergy, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10 MW, grid supply point Walpole.

Customer
Forenergy
Status
Connected
Capacity
10 MW
Technology
Bioenergy (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Walpole
Bulk supply point
March Grid 33kV
Voltage
33 kV
Date connected
20 Sept 2016
In a connection queue
No
Row last updated by the DNO
12 Aug 2022
Licence area
EPN
Address
Horseley Fen, Ely
Postcode
CB6 2AZ
Export MPAN
1050001044651

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.