Horam Solar Farm

Horam Solar Farm, Vantage RE, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 6.5 MW, grid supply point Ninfield.

Customer
Vantage RE
Status
Accepted to connect
Capacity
6.5 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Ninfield
Bulk supply point
Broad Oak Grid
Point of connection
TBC
Voltage
33 kV
Date accepted
13 Mar 2025
In a connection queue
Yes
Row last updated by the DNO
19 Jun 2026
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Horam Manor Farm, Heathfield
Postcode
TN21 0YD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.