Homefield Road

Homefield Road, Aggregated Micro Power Holdings PLC, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4 MW, grid supply point Pelham.

Customer
Aggregated Micro Power Holdings PLC
Status
Connected
Capacity
4 MW
Maximum import capacity
0.2 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Belchamp Grid 33kV
Point of connection
Haverhill Primary 11kV
Voltage
11 kV
Date connected
21 Jun 2021
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Haverhill
Postcode
CB9 8QU
Export MPAN
1050001021405

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.