Hill Farm

Hill Farm, Lark Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10.5 MW, grid supply point Wymondley.

Customer
Lark Energy Limited
Status
Connected
Capacity
10.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Letchworth Grid 33kV
Voltage
33 kV
Date connected
27 Mar 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Off Edworth Road, Langford
Postcode
SG18 9PJ
Export MPAN
1050000698283

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source