Folly Farm

Folly Farm, Hive Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 15 MW, grid supply point Sundon.

Customer
Hive Energy Limited
Status
Connected
Capacity
15 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Sundon
Bulk supply point
Aylesbury East Grid 33kV
Voltage
33 kV
Date connected
25 Mar 2015
In a connection queue
No
Row last updated by the DNO
14 Nov 2023
Licence area
EPN
Address
Long Marston
Postcode
HP23 4QY
Export MPAN
1050000822472

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.