Grid GuardianOpen the evidence in the app

Finmere Power

Finmere Power, Urban Reserve (AssetCo) Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.1 MW, grid supply point Ninfield.

Customer
Urban Reserve (AssetCo) Limited
Status
Connected
Capacity
4.1 MW
Maximum import capacity
0.14 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Ninfield
Point of connection
Eastbourne 11kV
Voltage
11 kV
Date connected
9 Jan 2021
In a connection queue
No
Row last updated by the DNO
15 May 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Finmere Road, Eastbourne
Postcode
BN22 8QJ
Export MPAN
1900092025159
Import MPAN
1900092025140

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.