Fenmarc

Fenmarc, Local Generation Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.5 MW, grid supply point Walpole.

Customer
Local Generation Limited
Status
Connected
Capacity
2.5 MW
Technology
Other (Other)
Flexible connection
No
Grid supply point
Walpole
Bulk supply point
March Grid 33kV
Point of connection
March Primary 11kV
Voltage
11 kV
Date connected
11 Aug 2011
In a connection queue
No
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Wisbech Road, March
Postcode
PE15 0BA
Export MPAN
1030078216564

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.