FDG A-16 Bury Green Lane Farm

FDG A-16 Bury Green Lane Farm, Abbey Group Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 5 MW, grid supply point Walpole.

Customer
Abbey Group Limited
Status
Connected
Capacity
5 MW
Maximum import capacity
0.1 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
Peterborough Central 33kV
Voltage
33 kV
Date connected
30 Mar 2016
In a connection queue
No
Row last updated by the DNO
14 Nov 2023
Licence area
EPN
Address
Funthams Lane, Peterborough
Postcode
PE7 2PB
Export MPAN
1050001036624

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.