Grid GuardianOpen the evidence in the app

FDG A-07 Greenvale March

FDG A-07 Greenvale March, Greenvale AP, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.5 MW, grid supply point Walpole.

Customer
Greenvale AP
Status
Connected
Capacity
1.5 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
March Grid 33kV
Point of connection
Chatteris Primary 11kV
Voltage
11 kV
Date connected
18 Nov 2014
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Ferry Road, March
Postcode
PE15 0UW
Export MPAN
1050000664016

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source