Envirtotech 3
Envirtotech 3, Bolney Green Energy Hub 3 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Bolney.
- Customer
- Bolney Green Energy Hub 3 Limited
- Status
- Accepted to connect
- Capacity
- 49.9 MW
- Technology
- Storage (Storage - Electrochemical (Batteries))
- Flexible connection
- No
- Grid supply point
- Bolney
- Voltage
- 132 kV
- Date accepted
- 21 Apr 2020
- Target energisation
- 31 Oct 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Jun 2024
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Bob Lane, Twineham
- Postcode
- RH17 5NH
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.