Elsenham Landfill

Elsenham Landfill, Viridor Waste Management Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1 MW, grid supply point Pelham.

Customer
Viridor Waste Management Limited
Status
Connected
Capacity
1 MW
Technology
Bioenergy (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Bishops Stortford Grid 33kV
Point of connection
Stansted Airport Main Pr 11kV
Voltage
11 kV
Date connected
12 Feb 2009
In a connection queue
No
Row last updated by the DNO
14 Nov 2024
Licence area
EPN
Address
Bishops Stortford
Postcode
CM22 6DJ
Export MPAN
1030058039810

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.