Grid GuardianOpen the evidence in the app

Dominic Petre Of Hutton Battery Bank

Dominic Petre Of Hutton Battery Bank, Solar Inc Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10 MW, grid supply point Warley.

Customer
Solar Inc Limited
Status
Connected
Capacity
10 MW
Maximum import capacity
10 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Warley
Bulk supply point
Shenfield Grid 33kV
Voltage
33 kV
Date connected
26 Nov 2019
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Mountnessing, Brentwood
Postcode
CM13 1BZ
Export MPAN
1050001915560

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source