Grid GuardianOpen the evidence in the app

Colbrans Farm

Colbrans Farm, Colbrans Solar ESS Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 39.9 MW, grid supply point Ninfield.

Customer
Colbrans Solar ESS Limited
Status
Accepted to connect
Capacity
39.9 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Ninfield
Bulk supply point
Lewes Grid 33kV
Voltage
33 kV
Date accepted
11 Feb 2021
Target energisation
31 Dec 2030
In a connection queue
Yes
Row last updated by the DNO
15 Apr 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Cow Lane, Laughton
Postcode
BN8 6BZ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.