Chiplow Wind Farm

Chiplow Wind Farm, E.ON Climate & Renewable UK Developmets Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12.5 MW, grid supply point Walpole.

Customer
E.ON Climate & Renewable UK Developmets Limited
Status
Connected
Capacity
12.5 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Walpole
Bulk supply point
Hempton Grid 33kV
Voltage
33 kV
Date connected
6 Jan 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Bagthorpe, Kings Lynn
Postcode
PE31 8SR
Export MPAN
1050000948031

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source