Grid GuardianOpen the evidence in the app

Cavendish Power

Cavendish Power, AGR, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 8 MW, grid supply point Wymondley.

Customer
AGR
Status
Connected
Capacity
8 MW
Maximum import capacity
0 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Stevenage Grid 33kV
Point of connection
Stevenage Primary 11kV
Voltage
11 kV
Date connected
19 Sept 2018
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Cavendish Road, Stevenage
Postcode
SG1 2EU
Export MPAN
1050001609381

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source