Grid GuardianOpen the evidence in the app

Bygrave Lodge Farm

Bygrave Lodge Farm, Powersystems UK Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.6 MW, grid supply point Wymondley.

Customer
Powersystems UK Limited
Status
Connected
Capacity
2.6 MW
Technology
Bioenergy (Steam-gas turbine (CCGT))
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Letchworth Grid 33kV
Point of connection
Letchworth Factory 11kV
Voltage
11 kV
Date connected
25 Sept 2014
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Baldock
Postcode
SG7 6QX
Export MPAN
1050000645468

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source