Broomfield Solar Farm
Broomfield Solar Farm, Low Carbon Solar Park 31 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 14 MW, grid supply point Bolney.
- Customer
- Low Carbon Solar Park 31 Limited
- Status
- Accepted to connect
- Capacity
- 14 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- Bolney
- Bulk supply point
- Bolney Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 22 Dec 2021
- Target energisation
- 31 Dec 2030
- In a connection queue
- Yes
- Row last updated by the DNO
- 15 Apr 2024
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Horsham
- Postcode
- RH13 8DL
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.