Grid GuardianOpen the evidence in the app

Brighton Road

Brighton Road, Ilos New Energy UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 15 MW, grid supply point Bolney.

Customer
Ilos New Energy UK Limited
Status
Accepted to connect
Capacity
15 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bolney
Voltage
33 kV
Date accepted
2 Sept 2026
In a connection queue
Yes
Row last updated by the DNO
13 Mar 2026
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Horsham
Postcode
RH13 8HG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source