Brielle Way Generation

Brielle Way Generation, UK Power Reserve Thames Steel Power Station, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 16 MW, grid supply point Kemsley.

Customer
UK Power Reserve Thames Steel Power Station
Status
Connected
Capacity
16 MW
Technology
Fossil - Oil (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Kemsley
Bulk supply point
Sheerness Grid 33kV
Voltage
33 kV
Date connected
22 Sept 2018
In a connection queue
No
Row last updated by the DNO
12 Aug 2022
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Thamesteel, Sheerness
Postcode
ME12 1TH
Export MPAN
1900091523125

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source