Bolney Solar

Bolney Solar, Enso Green Holdings Y Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 15 MW, grid supply point Bolney.

Customer
Enso Green Holdings Y Limited
Status
Accepted to connect
Capacity
15 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bolney
Bulk supply point
Steyning Grid
Point of connection
Steyning Grid 33kV
Voltage
33 kV
Date accepted
20 Dec 2021
Target energisation
31 Dec 2030
In a connection queue
Yes
Row last updated by the DNO
15 Apr 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Horsham Road, Steyning
Postcode
BN44 3AB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source