Bluebridge Industial Estate

Bluebridge Industial Estate, Tamar Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.4 MW, grid supply point Braintree.

Customer
Tamar Energy Limited
Status
Connected
Capacity
2.4 MW
Maximum import capacity
0 MW
Technology
Bioenergy (Steam-gas turbine (CCGT))
Flexible connection
No
Grid supply point
Braintree
Bulk supply point
Braintree Local 33kV
Point of connection
Halstead Primary 11kV
Voltage
11 kV
Date connected
9 Jan 2017
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Halstead
Postcode
CO9 2SZ
Export MPAN
1050000535729

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.