Grid GuardianOpen the evidence in the app

Biggleswade Wind Farm

Biggleswade Wind Farm, Co-Operative Group PLC, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20.5 MW, grid supply point Wymondley.

Customer
Co-Operative Group PLC
Status
Connected
Capacity
20.5 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Letchworth Grid 33kV
Voltage
33 kV
Date connected
30 Jul 2013
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Wymondley
Postcode
SG18 9QP
Export MPAN
1030083931142

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source