Grid GuardianOpen the evidence in the app

Beetley Landfill Site

Beetley Landfill Site is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.46 MW, grid supply point Norwich.

Status
Connected
Capacity
1.46 MW
Technology
Bioenergy (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Norwich
Bulk supply point
Sall Grid 33kV
Point of connection
East Dereham Primary 11kV
Voltage
11 kV
Date connected
27 Oct 2004
In a connection queue
No
Row last updated by the DNO
14 Nov 2024
Licence area
EPN
Address
Beetley
Postcode
NR20 4HU
Export MPAN
1030006718997

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source