Grid GuardianOpen the evidence in the app

(ANM) Thorney

(ANM) Thorney, FRV TH Powertek Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.99 MW, grid supply point Walpole.

Customer
FRV TH Powertek Limited
Status
Accepted to connect
Capacity
49.99 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Voltage
132 kV
Date accepted
4 Nov 2024
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
New Cut, Peterborough
Postcode
PE6 0TH

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source