Grid GuardianOpen the evidence in the app

(ANM) Stanground South Of Fletton Park

(ANM) Stanground South Of Fletton Park, Cambrideshire County Council, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12 MW, grid supply point Walpole.

Customer
Cambrideshire County Council
Status
Accepted to connect
Capacity
12 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
Peterborough Central 33kV
Voltage
33 kV
Date accepted
17 Jun 2020
Target energisation
31 Oct 2030
In a connection queue
Yes
Row last updated by the DNO
13 Sept 2024
Licence area
EPN
Address
Peterborough
Postcode
PE7 3BD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.