(ANM) Sedgeford Hall Estate

(ANM) Sedgeford Hall Estate, Regener8 SPV 2 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 16 MW, grid supply point Walpole.

Customer
Regener8 SPV 2 Limited
Status
Accepted to connect
Capacity
16 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
Kings Lynn Grid 33kV
Point of connection
Snettisham Primary 11kV
Voltage
33 kV
Date accepted
24 Jun 2020
In a connection queue
Yes
Row last updated by the DNO
14 Feb 2023
Licence area
EPN
Address
Fring Road, Kings Lynn
Postcode
PE31 7NE

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.